From Kansas Department of Transporation
The Cedar Creek bridge north of Toronto has been replaced, and K-105 in southwest Woodson County is now fully opened to traffic, according to the Kansas Department of Transportation.
The project began in May 2024 and faced delays related to geological conditions on site that required a partial redesign.
While both lanes on the bridge are open to traffic, the contractor still has minor work to complete, most of which will not impact traffic. For some of this work, the contractor may need to use flaggers, which may reduce traffic to one lane and result in minor delays.
B&B Bridge Company Inc., of St. Paul, is the primary contractor on the $4.9 million project.